top of page

Bi-Weekly Update
July 21, 2023

Bi-Weekly Update
July 7, 2023

Bi-Weekly Update
June 23, 2023

Bi-Weekly Update
April 21, 2023

Bi-Weekly Update
March 31, 2023

Bi-Weekly Update
March 17, 2023

Bi-Weekly Update
February 17, 2023

Bi-Weekly Update
January 20, 2023

Bi-Weekly Update
January 6, 2023

Bi-Weekly Update
December 23, 2022

Bi-Weekly Update
December 9, 2022

Bi-Weekly Update
November 11, 2022

Bi-Weekly Update
October 27, 2022

Bi-Weekly Update
September 16, 2022

Bi-Weekly Update
September 2, 2022

Bi-Weekly Update
August 19, 2022

Bi-Weekly Update
July 22, 2022

Lots 51-53 cabinets installed. Lots 48-50 painted and cabinets delivered. Lots 45-47 trim and cabinets. Lots 42-44 trim and countertops. Lots 40-41 insulation, ground floor decks, siding. Lots 37-39 rough in, ground floor decks, inspections next week. Lots 35-36 framing punch and rough in started. Lots 33-34 framing punch. Lots 28-32 framing complete, roofing started. Lots 24-27 ground floor framing. Lots 15-23 foundations and plumbing ready, pouring slabs 7/26. Cabana framing almost completed. Prepping site for grading and remaining site work.  Scheduling final utility and irrigation installation.

Bi-Weekly Update
July 8, 2022

Trim started on lots 42-46. Mechanical units are being set on lots 42-53. Rough ins completed lots on 40-41. Rough ins being installed on lots 37-39. Decks are built on all framed units and deck boards are down. Lots 28-32 are almost done being framed. Framing on the pool house is underway! Plumbing slabs on lots 15-23 completed. Concrete scheduled for next week. Siding will start on lots 37-41 next week. Framing will start on lots 24-27 today. Cabinets are being installed in lots 51-53. Countertops being installed in lots 42 and 44 today!

Bi-Weekly Update
June 24, 2022

Pulled strings for lots 15-23. Digging footings for lots 20-23. Framing continues on lots 28-32. Porch decks, handrail posts, framing punch and rough-in inspections on lots 33-41. Drywall finishing and siding on lots 51-53. Drywall hanging, metal roofs and siding on lots 48-50. Siding, cabinets, paint, railings, metal roofs on lots 45-47. Tile, cabinets, garage doors, trim, paint and railings on lots 42-44.

Bi-Weekly Update
June 10, 2022

Pergolas, post wraps and railings on Lots 42-44. Metal roofs installed. Painting on Lots 42-44. Drywall finishing in Lots 45-47. Insulation and framing in Lots 48-53. Mechanical and plumbing in Lots 37-41. Framing Lots 33-41. Finished roof on Lots 35-36. Started framing Lots 28-32.

Bi-Weekly Update
May 26, 2022

Framing decks on Lots 33-41 and siding Lots 48-53. Slab complete for Lots 24-27. Drywall installing and finishing in Lots 42-47. Plumbed the pool house.

Bi-Weekly Update
May 13, 2022

Pool cabana poles installed, plumbing on Lots 24-27, started back decks on Lots 37-41. Sheetrock being installed in Lots 42-44, decking, siding and roofing continues along with more dredging and walkway construction.

Bi-Weekly Update
April 28, 2022

Electrical and HVAC installs continue. Siding Lots 48-53. Framing almost complete on Lots 35 & 36! Slab has been poured for Lots 28-32. Strings and batter boards getting prepped for concrete on 24-27. We have the first round of concrete in the pool! Dredging crew is putting on some finishing touches along the creek front.

Bi-Weekly Update
April 18, 2022

Started decking on Lots 42-44. Siding continuing on Lots 45-50. Roofing on Lots 42-53 will be completed this week. Pool is getting closer – pouring concrete next week!

Bi-Weekly Update
March 30, 2022

Siding, roofing, framing, porch decks….pool! It’s a busy construction site.

Bi-Weekly Update
March 17, 2022

Framing, framing, framing! Windows are in on Lots 48-53 and exterior doors have been delivered. Siding continues on Lots 42-44. Grading and site work ongoing. Pool digging starts next week!

Bi-Weekly Update
March 7, 2022

Morgan’s Creek sea wall is complete. Completed walkway along NE side of basin entrance. Siding going on Lots 42-44. Garages poured for Lots 33-36. Framing continues on Lots 37-41 and Lots 48-53! Grading preparations are in final stages before digging the pool. The builders and developers are enjoying meeting everyone and making selections!

Bi-Weekly Update
February 4, 2022

Framing is just about complete at Lots 48-53 and windows have started going in Lots 42-47! Slabs are being poured at Lots 33-36 in the next few days and framing will begin on Lots 40-41 very soon. More progress has been made on the boardwalk and the marina is looking great. All progress is weather permitting. 

Bi-Weekly Update
January 21, 2022

Marina construction continues. There has been a lot of framing progress and windows are going in Lots 42 through 44. HVAC and plumbing have started in lots 42 through 47, as well!

Questions?

bottom of page